# Garden City Irrigation Canal Piping Project Moves Into Construction
- URL: https://www.bearlaketv.com/garden-city-irrigation-canal-piping-project-moves-into-construction/
- Published: 2026-11-09T23:59:37.000Z
- Updated: 2026-11-09T23:59:37.000Z
- Description: Crews are replacing open, earth-lined canal above the Marina and Harbor Village areas with 48-inch fused HDPE pipe.
- Author: Darren Eastman
- Tags: Garden City, Bear Lake, Construction, Water

GARDEN CITY — Crews have begun installing large-diameter pipe on the Hodges and Swan Creek irrigation canal system, replacing open earth-lined sections above the Marina and Harbor Village areas with 48-inch fused HDPE pipe.

The project covers two segments. The Marina section includes roughly 750 feet of 48-inch fused HDPE pipe installed by open trench, along with two concrete transition structures, valves, fittings, demolition of existing canal structures, and filling and grading of the old channel. The Harbor Village section includes about 1,600 feet of the same 48-inch pipe, one concrete transition structure, and similar demolition, valve, and grading work.

![](https://storage.ghost.io/c/04/7b/047b94fd-6519-4056-a170-ef7189e7eae9/content/images/2026/11/canal-piping-excavator-hillside.jpg)

An excavator works the hillside above homes along the canal route. Photo: Darren Eastman / Bear Lake TV

The project is owned by Hodges Irrigation Company and Swan Creek Canal Company. J-U-B Engineers is the design engineer. It was advertised for bids earlier this year under QuestCDN number 10051859 and is now under construction.

A Bureau of Reclamation WaterSMART Water and Energy Efficiency Grant supports the broader effort. Grant documents describe piping roughly 3,600 feet of canal overall, installing measuring structures, and adding a solar array. The project is expected to reduce annual seepage losses by about 555 acre-feet and lower the risk of canal failure on the hillside above homes and recreational facilities. It is also intended to reduce sediment reaching Bear Lake.

A 2021 water-loss study on the shared canal system documented high seepage rates. Past breaches in the Harbor Village area, reported in 2017 and 2023, underscored flooding and safety concerns when the open canal runs above developed ground.

Construction is scheduled outside the main irrigation season. Grant documents projected pipe installation continuing into 2026, with project closeout targeted later that year.

The work is part of a wider pattern across Utah in which irrigation companies are piping open canals to cut water losses, improve delivery control, and reduce risk to nearby property and water quality.

Sources: QuestCDN project posting #10051859; Bureau of Reclamation WaterSMART FY 2024 grant application (WEEG-155, Town of Garden City); 2021 water-loss study referenced in the grant application; prior local reporting on canal breaches affecting Harbor Village; Bear Lake Special Service District and Town of Garden City (local sewer and water providers).