Evanston Data Center Says It Has State Permits; Up to 250 Power-Plant Construction Jobs at Peak
Prometheus Hyperscale says its data center and power plant east of Evanston now have state permits. The power plant would need up to 250 construction workers at peak and keep 25 permanent jobs; no public report yet that construction has started.
EVANSTON, Wyo. — The large data center planned east of Evanston is still moving ahead, and the company behind it says the project now has its state permits. Prometheus Hyperscale said Oct. 15 that a letter from Wyoming's Industrial Siting Council confirmed construction and operating permits for both the data center and its on-site power facility. That is the company's account; Bear Lake TV has not yet seen the council's letter.
The campus would cover about 506 acres of ranchland roughly 12 miles east of Evanston. It is designed for 1.25 gigawatts of initial capacity with a path to 5 gigawatts, and would generate its own power with natural gas engines and turbines, off the public grid, with closed-loop cooling, according to the company.
The jobs. Up to 250 construction jobs would be available at the power plant's peak, including electricians, iron workers, pipe fitters, operating engineers, fiber techs, surveyors and concrete crews, the Uinta County Herald reported from the Sept. 15 meeting where county commissioners approved the plant's permit. Once complete, founder Trenton Thornock said, the power plant would support 25 permanent jobs, including facility techs, electrical and mechanical maintenance, system control and network operations, and site and security management.
The county has also permitted temporary workforce housing, run by Target Hyper/Scale, on county land next to Bear River State Park. It can house as many as 3,400 data center construction workers for up to five years, Cowboy State Daily reported in July.
When does work start? Prometheus has said construction would begin within six months of final permitting, with the full campus built in phases over 48 to 60 months. As of late August, construction had not begun, Cowboy State Daily reported, and Bear Lake TV found no public report that it has started since. Under the power-plant permit, the county must be notified when construction, defined as footings and utility duct work, begins, and it must start within five years.
Prometheus' focus on Evanston sharpened in late October, when the company dropped a separate plan in Natrona and Converse counties. "We are thrilled with our progress in Evanston with Uinta County and believe other additional locations in Wyoming offer a clearer path to permitting and community support," company president Trevor Neilson told Cowboy State Daily and WyoFile.
The $68.3 million community benefits package Bear Lake TV reported Nov. 8 still takes effect only after the developer signs a lease with its tenant, which has not been named, the Herald reported.
Sources: Prometheus Hyperscale, Oct. 15, 2026; Uinta County Herald via WyomingNews.com, Sept. 17 and Nov. 5, 2026; Cowboy State Daily, July 28, Aug. 25 and Oct. 28, 2026; WyoFile, Oct. 28, 2026; Prometheus Hyperscale news release, June 17, 2026. The feature image is an AI-generated illustration by Bear Lake OG, not a picture of the actual site.